#"Preparation of designer’s operating criteria and identification of special considerations to be observed during construction and [[operation]]
#"Preparation of designer’s operating criteria and identification of special considerations to be observed during construction and [[operation]]
#"Provisions for the automatic, independent review by competent individuals of all design decisions, methods, procedures, and results related to dam safety
#"Provisions for the automatic, independent review by competent individuals of all design decisions, methods, procedures, and results related to dam safety
#"Provisions to revise the design to make it compatible with conditions encountered during construction." <ref name="Small Dams">[[Design of Small Dams| Design of Small Dams (United States Bureau of Reclamation, 1987)]]</ref>  
#"Provisions to revise the design to make it compatible with conditions encountered during construction." <ref name="Small Dams">[[Design of Small Dams | Design of Small Dams, USBR, 1987]]</ref>  


<!-- For information on notation for in text citations visit https://www.mediawiki.org/wiki/Help:Cite  Or simply enclose the citation as shown <ref> citation </ref> in the location of the in text mention. Citations will automatically populate below-->
<!-- For information on notation for in text citations visit https://www.mediawiki.org/wiki/Help:Cite  Or simply enclose the citation as shown <ref> citation </ref> in the location of the in text mention. Citations will automatically populate below-->

Revision as of 18:39, 19 December 2022


Site planning for a new dam or rehabilitation design "should be developed in accordance with state-of-the-art design techniques and construction practices and in a manner commensurate with its size, function, geologic setting, and potential hazard classification. Careful attention must be given to the following planning and design considerations":

  1. "Selection of the dam site
  2. "Estimation of the PMF and selection of the IDF
  3. "Identification of earthquake source area and structure, estimation of MCE’s, and identification of earthquake-related safety concerns
  4. "Development of a site-specific geotechnical exploration program
  5. "Design of the foundation, dam, and appurtenant structures
  6. "Design of a system of instrumentation to monitor the performance of the dam, foundation, and appurtenant structures
  7. "Development of an initial reservoir-filling and surveillance plan and of reservoir drawdown criteria
  8. "Preparation of designer’s operating criteria and identification of special considerations to be observed during construction and operation
  9. "Provisions for the automatic, independent review by competent individuals of all design decisions, methods, procedures, and results related to dam safety
  10. "Provisions to revise the design to make it compatible with conditions encountered during construction." [1]