<!-- Delete any sections that are not necessary to your topic. Add pictures/sections as needed --> | <!-- Delete any sections that are not necessary to your topic. Add pictures/sections as needed --> | ||
Site planning for a new dam or [[rehabilitation]] design "should be developed in accordance with state-of-the-art design techniques and [[construction]] practices and in a manner commensurate with its size, function, geologic setting, and potential hazard classification. Careful attention must be given to the following planning and design considerations: | Site planning for a new dam or [[rehabilitation]] design "should be developed in accordance with state-of-the-art design techniques and [[construction]] practices and in a manner commensurate with its size, function, geologic setting, and potential hazard classification. Careful attention must be given to the following planning and design considerations": | ||
#Selection of the dam site | #"Selection of the dam site | ||
#Estimation of the PMF and selection of the IDF | #"Estimation of the PMF and selection of the IDF | ||
#Identification of earthquake source area and structure, estimation of MCE’s, and identification of earthquake-related safety concerns | #"Identification of earthquake source area and structure, estimation of MCE’s, and identification of earthquake-related safety concerns | ||
#Development of a site-specific geotechnical exploration program | #"Development of a site-specific [[Geotechnical Exploration|geotechnical exploration]] program | ||
#Design of the foundation, dam, and appurtenant structures | #"Design of the foundation, dam, and appurtenant structures | ||
#Design of a system of instrumentation to monitor the performance of the dam, foundation, and appurtenant structures | #"Design of a system of instrumentation to monitor the performance of the dam, foundation, and appurtenant structures | ||
#Development of an initial reservoir-filling and surveillance plan and of reservoir drawdown criteria | #"Development of an initial reservoir-filling and surveillance plan and of [[Reservoir Drawdown|reservoir drawdown]] criteria | ||
#Preparation of designer’s operating criteria and identification of special considerations to be observed during construction and [[operation]] | #"Preparation of designer’s operating criteria and identification of special considerations to be observed during construction and [[operation]] | ||
#Provisions for the automatic, independent review by competent individuals of all design decisions, methods, procedures, and results related to dam safety | #"Provisions for the automatic, independent review by competent individuals of all design decisions, methods, procedures, and results related to dam safety | ||
#Provisions to revise the design to make it compatible with conditions encountered during construction." <ref name="Small Dams">[[Design of Small Dams| Design of Small Dams (United States Bureau of Reclamation, 1987)]]</ref> | #"Provisions to revise the design to make it compatible with conditions encountered during construction." <ref name="Small Dams">[[Design of Small Dams| Design of Small Dams (United States Bureau of Reclamation, 1987)]]</ref> | ||
<!-- For information on notation for in text citations visit https://www.mediawiki.org/wiki/Help:Cite Or simply enclose the citation as shown <ref> citation </ref> in the location of the in text mention. Citations will automatically populate below--> | <!-- For information on notation for in text citations visit https://www.mediawiki.org/wiki/Help:Cite Or simply enclose the citation as shown <ref> citation </ref> in the location of the in text mention. Citations will automatically populate below--> |
Revision as of 20:57, 12 December 2022
Site planning for a new dam or rehabilitation design "should be developed in accordance with state-of-the-art design techniques and construction practices and in a manner commensurate with its size, function, geologic setting, and potential hazard classification. Careful attention must be given to the following planning and design considerations":
- "Selection of the dam site
- "Estimation of the PMF and selection of the IDF
- "Identification of earthquake source area and structure, estimation of MCE’s, and identification of earthquake-related safety concerns
- "Development of a site-specific geotechnical exploration program
- "Design of the foundation, dam, and appurtenant structures
- "Design of a system of instrumentation to monitor the performance of the dam, foundation, and appurtenant structures
- "Development of an initial reservoir-filling and surveillance plan and of reservoir drawdown criteria
- "Preparation of designer’s operating criteria and identification of special considerations to be observed during construction and operation
- "Provisions for the automatic, independent review by competent individuals of all design decisions, methods, procedures, and results related to dam safety
- "Provisions to revise the design to make it compatible with conditions encountered during construction." [1]
Citations:
Revision ID: 5187
Revision Date: 12/12/2022