Revision as of 20:11, 27 June 2022 by Camrenbt (talk | contribs) (Created page with "<!--Example Page --> <div style= "text-align:center;"> <!-- Add message here --> ''Message: Wells are only effective if they are strategically placed and coordinated with each other'' </div> ----</br> <!-- Add body paragraphs here --> Lake Frances Dam was built in 1909, is 64 feet high, and stores 105,000 acre feet. Lake frances was ungoing a major rehab of the outlet works – involved replacement of the upstream section and sliplining the downstream section with steel...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

Message: Wells are only effective if they are strategically placed and coordinated with each other



Lake Frances Dam was built in 1909, is 64 feet high, and stores 105,000 acre feet. Lake frances was ungoing a major rehab of the outlet works – involved replacement of the upstream section and sliplining the downstream section with steel pipe. A canal company was responsible for earthwork and dewatering and a contractor was hired for the sliplining operations.

Lessons learned:

  • Dewatering can make or break a project, especially with fall construction – anticipate problems in advance
  • You can tell right away if your dewatering system isn't working – don’t delay in trying something else.
  • Calling in the experts can save you money in the long run.
  • Wells are only effective if they are strategically placed and coordinated with each other