(Created page with "{{Example Page |message= <!-- Add message statement --> Message: Concrete bedding installs relatively quickly, without the need for compaction under pipe haunces |body= <!-- Add body paragraphs --> Concrete bedding was used successfully in this Montana dam. Placing and encasing the 170-ft, 48-inch concrete outlet conduit was estimated to cost $133,000 (2013 cost). Six days of work effort were required to construct the foundation of the spillway riser, excavate the outle...")
 
No edit summary
Line 1: Line 1:
{{Example Page
<!--Example Page -->
|message=
<div style= "text-align:center;">
<!-- Add message statement -->
<!-- Add message here -->
Message: Concrete bedding installs relatively quickly, without the need for compaction under pipe haunces
''Message: Concrete bedding installs relatively quickly, without the need for compaction under pipe haunces''
 
</div>
|body=
----</br>
<!-- Add body paragraphs -->
<!-- Add body paragraphs here -->
Concrete bedding was used successfully in this Montana dam. Placing and encasing the 170-ft, 48-inch concrete outlet conduit was estimated to cost $133,000 (2013 cost). Six days of work effort were required to construct the foundation of the spillway riser, excavate the outlet conduit trench, and place the outlet conduit (including concrete bedding placement).
Concrete bedding was used successfully in this Montana dam. Placing and encasing the 170-ft, 48-inch concrete outlet conduit was estimated to cost $133,000 (2013 cost). Six days of work effort were required to construct the foundation of the spillway riser, excavate the outlet conduit trench, and place the outlet conduit (including concrete bedding placement).


|pictures=
<gallery mode="slideshow" >
<!-- Add picture files and captions for slideshow -->
<!-- Add image files here -->
File:CBI1.jpg|This photo shows the excavated embankment with the bottom compacted. The pipe trench will be excavated from this compacted surface.
File:CBI1.jpg|This photo shows the excavated embankment with the bottom compacted. The pipe trench will be excavated from this compacted surface.
File:CBI2.jpg|Excavating pipe trench.
File:CBI2.jpg|Excavating pipe trench.
Line 21: Line 21:
File:CBI10.jpg|Installed pipe with concrete bedding and cap.
File:CBI10.jpg|Installed pipe with concrete bedding and cap.
File:CBI11.jpg|Example detail of bedding configuration.
File:CBI11.jpg|Example detail of bedding configuration.
</gallery>


}}
[[Category:Example Pages]]
{{Revhistinf}}

Revision as of 17:05, 24 June 2022

Message: Concrete bedding installs relatively quickly, without the need for compaction under pipe haunces



Concrete bedding was used successfully in this Montana dam. Placing and encasing the 170-ft, 48-inch concrete outlet conduit was estimated to cost $133,000 (2013 cost). Six days of work effort were required to construct the foundation of the spillway riser, excavate the outlet conduit trench, and place the outlet conduit (including concrete bedding placement).