ASDSO Dam Safety Toolbox

Slipline Example 1: Difference between revisions

From ASDSO Dam Safety Toolbox
Jump to: navigation, search
No edit summary
No edit summary
 
Line 1: Line 1:
<div style= "text-align:center;">''Message: Sliplining large diameter pipe takes extra planning.''</div>
[[Category:Rehab vs. Replacement Outlet Works]]
----</br>
----
''' ''Message: Sliplining large diameter pipe takes extra planning.'' '''


<gallery mode="slideshow">
<gallery mode="slideshow">
File:1SE1.jpg|As part of a major dam rehabilitation project, an 84-inch arch concrete outlet was slip lined with a 72-inch diameter welded steel pipe.
File:1SE1.jpg|As part of a major dam [[rehabilitation]] project, an 84-inch arch concrete outlet was slip lined with a 72-inch diameter welded steel pipe.
File:1SE2.jpg|Due to the pipe size and other construction restrictions, the steel pipe was inserted into the outlet in multiple sections. A trolley system for moving the pipe up the conduit was constructed by the contractor in order to both increase safety and to minimize damage to the pipe
File:1SE2.jpg|Due to the pipe size and other [[construction]] restrictions, the steel pipe was inserted into the outlet in multiple sections. A trolley system for moving the pipe up the conduit was constructed by the contractor in order to both increase safety and to minimize damage to the pipe
File:1SE3.jpg|After placement, the joints between the sections of pipe were welded. Each weld was tested to ensure there were no defects in the joints.
File:1SE3.jpg|After placement, the joints between the sections of pipe were welded. Each weld was tested to ensure there were no defects in the joints.
File:1SE4.jpg|Grout injection gallery.
File:1SE4.jpg|Grout injection gallery.
File:1SE5.jpg|This sliplining project had a relatively large annular space to grout. Grout was placed in four separate lifts using a grouting gallery in order to control fluid pressure on the pipe, floatation of the pipe, bleed water from the grout, and the heat produced during the grout curing process.
File:1SE5.jpg|This sliplining project had a relatively large annular space to grout. Grout was placed in four separate lifts using a [[grouting]] gallery in order to control fluid pressure on the pipe, floatation of the pipe, bleed water from the grout, and the heat produced during the grout curing process.


</gallery>
</gallery>

Latest revision as of 00:27, 2 December 2022


Message: Sliplining large diameter pipe takes extra planning.

Note: The content on this page was originally created as part of DamOutletWorks.org (DOWL, 2018). It has subsequently been updated and reformatted as part of the Dam Safety Toolbox.
Revision ID: 4699
Revision Date: 12/02/2022