Downstream Control: Difference between revisions
(Created page with "Flow control facilities located at the downstream end of a conduit, when closed, subject the entire conduit to the full reservoir head and the possibility of high pressure leaks, piping along the conduit, and subsequent failure of the embankment. Special design considerations are necessary for dams with downstream control. A common recommendation is to house the conduit in a concrete-lined tunnel or to encase the conduit in concrete. Outlet facilities with downstream con...") |
No edit summary |
||
Line 10: | Line 10: | ||
Is an alternate means to inspect the conduit available? | Is an alternate means to inspect the conduit available? | ||
*Access for conduit inspection is limited. Providing an alternate way to access the conduit is important. | *Access for conduit inspection is limited. Providing an alternate way to access the conduit is important. | ||
==Energy Dissipation== | ==Energy Dissipation Structure Types== | ||
*[[Energy Dissipation | *[[Accounting for Energy Dissipation]] | ||
==Cautions== | ==Cautions== | ||
*[[⚠ Include an Upstream Gate/Valve]] | *[[⚠ Include an Upstream Gate/Valve]] |
Revision as of 22:25, 24 June 2022
Flow control facilities located at the downstream end of a conduit, when closed, subject the entire conduit to the full reservoir head and the possibility of high pressure leaks, piping along the conduit, and subsequent failure of the embankment. Special design considerations are necessary for dams with downstream control. A common recommendation is to house the conduit in a concrete-lined tunnel or to encase the conduit in concrete. Outlet facilities with downstream control should also have an emergency gate upstream of the conduit.
Considering Downstream Control? Considerations and Questions to Ask
Is there any chance of leakage through joints?
- Fusion welded HDPE, steel, and iron pipe provide adequate joints when pressurized.
- Bell and Spigot PVC pipe is generally not recommended because leakage is possible.
- Corrugated metal is not recommended because leakage at banding is highly probable.
Is the current upstream control subject to ice and operational damage?
- Downstream control is an option for problematic upstream control systems (For example, where ice damage is common). Center control should also be considered, noting that adding center control where it doesn’t already exist can involve significant excavation into the embankment. Downstream control can be added with minimal impact to embankment.
Is an alternate means to inspect the conduit available?
- Access for conduit inspection is limited. Providing an alternate way to access the conduit is important.
Energy Dissipation Structure Types
Cautions