ASDSO Dam Safety Toolbox

Gates/Bulkheads: Difference between revisions

From ASDSO Dam Safety Toolbox
Jump to: navigation, search
No edit summary
 
(2 intermediate revisions by 2 users not shown)
Line 6: Line 6:
| [[Image:tainter1.jpg|350px|x350px|link=On-Demand Webinar: Introduction to Spillway Gates]]
| [[Image:tainter1.jpg|350px|x350px|link=On-Demand Webinar: Introduction to Spillway Gates]]
|-
|-
|style="text-align:center; font-size:90%;"| Learn more about gates from this [[On-Demand Webinar: Introduction to Spillway Gates|On-Demand Webinar]]
|style="text-align:center; font-size:90%;"| Image Source: [https://commons.wikimedia.org/wiki/File:Rapel_Dam_Tainter_Gate_2009.jpg Wikimedia]
Learn more about gates from this [[On-Demand Webinar: Introduction to Spillway Gates|On-Demand Webinar]]
|}
|}


Line 16: Line 17:


''' ''Gate Passageway Requirements:'' ''' "Normally, when reservoir outlet flows require regulation, the following are provided:  
''' ''Gate Passageway Requirements:'' ''' "Normally, when reservoir outlet flows require regulation, the following are provided:  
*Two or more gate passages such that if one passage is inoperative, a reasonable flow regulation as pertains to project purposes is obtained.  
*Two or more gate passages such that if one passage is inoperative, a reasonable [[Flow Regulation|flow regulation]] as pertains to project purposes is obtained.  
*Emergency gate provision (tandem or transferable) for each service gate passage so that if a service gate is inoperative in any position, closure of the gate passage can be made with the emergency gate for any pool level.  
*Emergency gate provision (tandem or transferable) for each service gate passage so that if a service gate is inoperative in any position, closure of the gate passage can be made with the emergency gate for any pool level.  


*Bulkhead provisions for each gate passage for inspection and maintenance of the service and emergency gates. At a minimum, the bulkheads must be capable of being installed at the lowest pool elevation that has a reasonable frequency and length of occurrence sufficient for inspection and repair purposes." <ref name="EM 1110-2-1602">[[Hydraulic Design of Reservoir Outlet Works (EM 1110-2-1602) | EM 1110-2-1602 Hydraulic Design of Reservoir Outlet Works, USACE, 1980]]</ref>  
*Bulkhead provisions for each gate passage for inspection and maintenance of the service and emergency gates. At a minimum, the bulkheads must be capable of being installed at the lowest pool elevation that has a reasonable frequency and length of occurrence sufficient for inspection and repair purposes." <ref name="EM 1110-2-1602">[[Hydraulic Design of Reservoir Outlet Works (EM 1110-2-1602) | Hydraulic Design of Reservoir Outlet Works (EM 1110-2-1602), USACE, 1980]]</ref>  


''' ''Gate Slots:'' ''' "The guide slots of rectangular gates produce a discontinuity in sidewalls which may cause [[cavitation]], unless specially designed. It has been common practice to use metal-liner plates downstream from the gate slots to protect the concrete from the erosive action of cavitation." <ref name="EM 1110-2-1602"/>  
''' ''Gate Slots:'' ''' "The guide slots of rectangular gates produce a discontinuity in sidewalls which may cause [[cavitation]], unless specially designed. It has been common practice to use metal-liner plates downstream from the gate slots to protect the concrete from the erosive action of cavitation." <ref name="EM 1110-2-1602"/>  
Line 56: Line 57:


<noautolinks>==Best Practices Resources==</noautolinks>
<noautolinks>==Best Practices Resources==</noautolinks>
{{Document Icon}} [[Design Standards No. 14: Appurtenant Structures for Dams (Ch. 4: General Outlet Works Design Considerations)|Design Standards No. 14: Appurtenant Structures for Dams (Ch. 4: General Outlet Works Design Considerations), USBR, 2022]]
{{Document Icon}} [[Design Standards No. 14: Appurtenant Structures for Dams (Ch. 4: General Outlet Works Design Considerations)|Design Standards No. 14: Appurtenant Structures for Dams (Ch. 4: General Outlet Works Design Considerations), USBR]]
{{Document Icon}} [[Design Standards No. 6: Hydraulic and Mechanical Equipment (Ch. 6: Bulkhead Gates and Stoplogs) | Design Standards No. 6: Hydraulic and Mechanical Equipment (Ch. 6: Bulkhead Gates and Stoplogs), USBR, 2018]]
{{Document Icon}} [[Design Standards No. 6: Hydraulic and Mechanical Equipment (Ch. 6: Bulkhead Gates and Stoplogs) | Design Standards No. 6: Hydraulic and Mechanical Equipment (Ch. 6: Bulkhead Gates and Stoplogs), USBR]]
{{Document Icon}} [[Hydraulic Design of Reservoir Outlet Works (EM 1110-2-1602) | Hydraulic Design of Reservoir Outlet Works (EM 1110-2-1602), USACE, 1980]]
{{Document Icon}} [[Hydraulic Design of Reservoir Outlet Works (EM 1110-2-1602) | Hydraulic Design of Reservoir Outlet Works (EM 1110-2-1602), USACE]]


==Trainings==
==Trainings==

Latest revision as of 21:05, 18 July 2023


Image Source: Wikimedia

Learn more about gates from this On-Demand Webinar

Gates and bulkheads are movable water barriers for the control of water. Gates are typically permanent features and include a wide range of types and sizes. Bulkheads are typically used either for temporary closure of a channel or conduit before dewatering it for inspection or maintenance or for closure against flowing water when the head difference is small, e.g., for diversion tunnel closure.

Components of Gates/Bulkheads

While there are many different types and sizes of gates and bulkheads, they often share similar components. These can include gate slots, gate recesses, gate seats, passageway liners, and air vents. Additionally, it is often required to design and construct redundant systems with at least two gates to allow for partial operation of the system in an emergency should one of the gates become inoperable.

Gate Passageway Requirements: "Normally, when reservoir outlet flows require regulation, the following are provided:

  • Two or more gate passages such that if one passage is inoperative, a reasonable flow regulation as pertains to project purposes is obtained.
  • Emergency gate provision (tandem or transferable) for each service gate passage so that if a service gate is inoperative in any position, closure of the gate passage can be made with the emergency gate for any pool level.
  • Bulkhead provisions for each gate passage for inspection and maintenance of the service and emergency gates. At a minimum, the bulkheads must be capable of being installed at the lowest pool elevation that has a reasonable frequency and length of occurrence sufficient for inspection and repair purposes." [1]

Gate Slots: "The guide slots of rectangular gates produce a discontinuity in sidewalls which may cause cavitation, unless specially designed. It has been common practice to use metal-liner plates downstream from the gate slots to protect the concrete from the erosive action of cavitation." [1]

Gate Recess: "Hydraulically operated control gates recess into bonnets and cable-suspended gates into wet wells. The necessary dimensional clearances for gate operation are usually based on mechanical and structural requirements rather than hydraulic. The primary hydraulic consideration is the relative upstream and downstream clearance at the roof recess when the gate passage is operated at part gate opening. The upstream clearance at the roof should be appreciably larger than the downstream clearance to assure maintenance of a hydrostatic head in the well or bonnet for gate stability. If the downstream clearance exceeds the upstream clearance the gate well can be sucked dry and the gate may float or catapult or oscillate under certain operating conditions." [1]

Gate Seats: "In general, the gate seat is flush with the floor of the gate passage." [1]

Steel Liners: "Steel liners in concrete conduits have been used where experience indicates cavitation is likely to occur such as downstream from control gates and valves where a high-velocity jet occurs. For head above 150 feet, no liner should be required. If a liner is necessary, it should not terminate at a monolith joint or in a transition." [1]

Air Vents: "Control valves and gates that are located a considerable distance upstream from the exit (i.e., do not discharge into the atmosphere) require air vents. An air vent is required for each service gate. Air vents are not required for emergency gates when those gates are located immediately upstream of air-vented service gates. Extreme caution must be observed if the emergency gate is used for regulation. Air demand will create very low pressures in the service gate recess. The attendant conditions must be carefully analyzed to prevent damage and/or danger to personnel." [1]

Types of Gates/Bulkheads

As a result of varying purposes of dams, as well as the unique site conditions that accompany each particular dam, there are a wide variety of types of gates or bulkheads. Some of the most common types include vertical lift gates, roller gates, hinged or flap gates, or tainter or radial gates. In the design process of a gated spillway system, it is necessary to weigh the advantages and disadvantages of using each type of gates in the particular operating conditions expected at the dam.

“Gated spillways include drop inlet, free overfall, ogee crest, side-channel and bathtub, tunnel inlet, various shaped weirs, and orifice. These control structures are associated with regulated releases and suited for service, auxiliary, and emergency spillways. The most frequently used gates include radial gates, drum gates, wheel-mounted gates, and crest gates. Examples of these gated spillways include:

  • Gated drop inlet spillway: This type of control structure is mostly associated with a service spillway with radial gates. An example of a gated drop inlet spillway is Reclamation’s Gibson Dam (concrete). Other examples include the service spillways with ring gates at Reclamation’s Hungry Horse and Owyhee Dams (both concrete).
  • Gated free overfall spillway: This type of control structure is mostly associated with a service spillway with roller gates. An example of a gated free overall spillway is Reclamation’s Parker Dam (concrete).
  • Gated ogee crest spillways: This type of control structure is associated with a service and auxiliary spillway with gates. Examples of gated ogee crest spillways are Reclamation’s Shasta Dam (concrete) with drum gates and auxiliary spillway with radial gates at Reclamation’s Stewart Mountain Dam (concrete). Other examples include service and emergency spillways with radial gates at Reclamation’s Folsom Dam (composite) and the service spillway with fixed-wheel gates at Reclamation’s Keswick Dam (composite).
  • Gated side-channel spillway: This type of control structure is mostly associated with a service spillway with gates. An example of a gated side-channel spillway is Reclamation’s Arrowrock Dam (concrete), which has drum gates.
  • Gated tunnel inlet spillway: This type of control structure is mostly associated with a service spillway with gates. An example of a gated tunnel inlet spillway is Reclamation’s Seminoe Dam (concrete) with fixed wheel gates. Other examples include the service spillways with radial gates at Reclamation’s Glen Canyon Dam and the service spillways with drum gates at Reclamation’s Hoover Dam.
  • Gated various shaped weir spillway: This type of control structure is mostly associated with a service spillway with gates. An example of a gated various shaped weir spillway is Reclamation’s Hyrum Dam (embankment) with radial gates.
  • Gated orifice spillway: With this type of control structure, flow is typically released from the spillway by one of two approaches: 1) A free jet is released downstream of the gates and typically is stilled by a plunge pool, 2) Flows will be released to a conveyance feature (such as a chute, conduit, or tunnel) and/or terminal structure."[2]

Life Cycle of Gates/Bulkheads

  1. Design and Construction of Gates/Bulkheads
  2. O&M of Gates/Bulkheads


Best Practices Resources

Design Standards No. 14: Appurtenant Structures for Dams (Ch. 4: General Outlet Works Design Considerations), USBR

Design Standards No. 6: Hydraulic and Mechanical Equipment (Ch. 6: Bulkhead Gates and Stoplogs), USBR

Hydraulic Design of Reservoir Outlet Works (EM 1110-2-1602), USACE