Step 2 of Pre-Analysis Communication: Develop Scope of Work
From ASDSO Dam Safety Toolbox
Once each of the aforementioned items have been evaluated and project objectives are understood, the owner and/or modeler will have the key information necessary to develop an adequate scope of work for the modeling effort. The scope of work should include all tasks needed to fulfill the model’s purpose.
Up Next: Step 3 of Pre-Analysis Communication: Obtain Concurrence from Regulatory Agency
Development of this page was sponsored by the Montana Department of Natural Resources & Conservation with funding from the FEMA Assistance to States Grant Program.