ASDSO Dam Safety Toolbox

Concrete Bedding is Easier to Bed than Clay

From ASDSO Dam Safety Toolbox
Revision as of 20:47, 15 September 2022 by Grichards (talk | contribs)
Jump to: navigation, search

Message: Concrete bedding installs relatively quickly, without the need for compaction under pipe haunces



Concrete bedding was used successfully in this Montana dam. Placing and encasing the 170-ft, 48-inch concrete outlet conduit was estimated to cost $133,000 (2013 cost). Six days of work effort were required to construct the foundation of the spillway riser, excavate the outlet conduit trench, and place the outlet conduit (including concrete bedding placement).


Note: The content on this page was originally created as part of DamOutletWorks.org (DOWL, 2018). It has subsequently been updated and reformatted as part of the Dam Safety Toolbox.
Revision ID: 3179
Revision Date: 09/15/2022