''' ''Message: It may not be possible to rehabilitate severely deteriorated pipes.'' '''
''Message: It may not be possible to rehabilitate severely deteriorated pipes.''
 
</div>
In this [[Alaska]] dam, the principal outlet conduit was in need of [[rehabilitation]]. The pipe was a good candidate for sliplining and the condition of the pipe allowed for a successful rehabilitation.
----</br>
<!-- Add body paragraphs here -->
In this Alaska dam, the principal outlet conduit was in need of rehabilitation. The pipe was a good candidate for sliplining and the condition of the pipe allowed for a successful rehabilitation.


However, the dam also had an auxiliary overflow conduit that was in need of rehabilitation. As shown in the images below, the pipe was in poor condition and sliplining was not an option. Ultimately, the auxiliary overflow conduit could not be rehabilitated and the pipe was abandoned in place using a cellular grout.
However, the dam also had an auxiliary overflow conduit that was in need of rehabilitation. As shown in the images below, the pipe was in poor condition and sliplining was not an option. Ultimately, the auxiliary overflow conduit could not be rehabilitated and the pipe was abandoned in place using a cellular grout.

Latest revision as of 00:36, 2 December 2022


Message: It may not be possible to rehabilitate severely deteriorated pipes.

In this Alaska dam, the principal outlet conduit was in need of rehabilitation. The pipe was a good candidate for sliplining and the condition of the pipe allowed for a successful rehabilitation.

However, the dam also had an auxiliary overflow conduit that was in need of rehabilitation. As shown in the images below, the pipe was in poor condition and sliplining was not an option. Ultimately, the auxiliary overflow conduit could not be rehabilitated and the pipe was abandoned in place using a cellular grout.